To consider the report of the Project Officer.
Minutes:
The committee received the report of the Project Officer in respect of a replacement heating system at Burwell Hall.
Members thanked the Project Officer for such a detailed report and considered the options outlined. The committee expressed a preference for a Fuel Cell CHP Boiler as it offered best value for money and would require less works at the hall. It was noted that it was a relatively new technology and requested that delegation be given to finalise the scheme subject to a satisfactory case study being received.
The committee noted that the Parks & Recreation Committee had agreed the refurbishment of the changing rooms on the site and both projects would need to run concurrently.
Resolved:
1. That, the Fuel Cell CHP Boiler option be approved: and
2. That, the decision be delegated to the Town Clerk in consultation with the Chair of the Committee and Leader of the Council subject to a satisfactory case study and the feasibility study for the changing room works.