Corn Exchange - Decoration and Damp Works

To consider the report of the Operations & Estates Advisor.

Minutes:

The report of the Operations & Estates Advisor was considered.

 

Members noted that the exterior decoration could be delayed for a couple of years to allow budgets to be allocated for the works.

 

In respect of damp works members considered the quotes submitted by contractors. It was agreed that Quote 1 provided the best option and would be a permanent solution. Clarification was given that the damp works would not impact on other developments at the Corn Exchange and any internal redecoration needed could be undertaken by the Works Team.

 

Recommended:

 

That, Quote 1 as detailed in the confidential appendix to the report be accepted.

 