Agenda item

The Leys - Skate Park

To receive the report of the Project Officer.

Minutes:

Consideration was given to the report of the Project Officer.

 

The committee considered the current position with regard to community involvement, design options and budget allocated for the skate park project. Members agreed the Town Council should undertake a full redevelopment of the site; new equipment would be preferable, if possible, and a tender process should be commenced. It was noted that the allocated budget was £100k and contractors should be asked to quote within that but if quotes were higher then additional finance or grant funding may need to be considered.

 

Recommended:

 

1.       That, a tender process for the redevelopment of The Leys skate park be commenced; and

2.       That, once the tenders are received the financial options be considered if quotes are above the allocated budget

 

Supporting documents: